Infrastructure

 

Infrastructure
I
Area of land  allotted (in acres)
 
Whether land transferred in the Name of Samiti
 
Vidyalaya shifted to permanent buildings on
 
 
:31.14 (Acres)
 
:Yes
 
 
:Shifted
 
ii
Status of Boundary Wall
 
a.  Brick Wall
b.  Barbed wire fencing
 
 
: (Completed)
 
Completed
Complete
 
 
iii
Permanent buildings constructed
 
 
: (CBRI pattern)
 
iv
School building
 
Yet To be Completed
 
: Complete
 
v
Dormitories
:  Boys 12   Nos.
   with Warden Residence  06   Nos.
 
 
 
 
:  Girls 08  Nos.
   with Warden Residence  04  Nos.
 
 
vi
Kitchen/dining Hall
 
No. of shifts required for all students  to take food
 
 
:  Complete Area ______
 
 
    One
vii
Principal Residence
 
 
01 No.
 
viii
Staff Quarters
 
 
 
 
:COMPLETED

  
ix
M.P. Hall
 
: not available
x
Workshop
 
: not available
xi
Type of O.H. Tank
 
Its capacity
 
Present Status
 
Completed
: Column based
 
:  _______ litres
 
: Working satisfactory
xii
U.G. tank
 
Its capacity
 
Present Status
 
: Completed
:  _______ litres
 
: Working satisfactory
xiii
D.G. Set
 
 
 
 
:  Available
: Cummins India (limited) make
:   15-25 KV
: Working
: Year of procurement2007-2008
 
xiv
Sewage Pump
 
: NOT AVAILABLE
xv
Water Pump
 
 
: Available
xvi
Electrification
 
Electric connection
Sub Station building
Street lighting
 
Numbers of hrs. during day when power supply is available on an average.
 
 
 
 :  Urban feader
:  Complete
: __________ Nos. of Poles
 
: 24 hrs.
  
xvii
Playfields
 
400 metre track
40 x 30 metre basket ball court
40 x 30 metre volley ball court
 
 
 
: Available
:  ___2____Nos.   – Available
:  ___2____Nos.   – Available
 
xviii
Water supply
Tube Well
Hand pump
Connection from PHED
 
 
completed
: Potable,  ___02___  working
: Potable, ___Nil___
: NO
xix
Rajiv Gandhi Smriti Van
 
:  Available & Maintained
xx
Fire fighting arrangement
 
:  Working
xxi
Last date of cleaning of
(a)   Septic tank
(b)   Water tanks
 completed
: JUNE 2015
: JUNE 2015
xxii
Whether area around transformer is closed by BOUNDARY WALL
:    YES
xxiii
Whether open wells, if any, are covered from top
:   Yes, Covered by fencing
xxiv
Works taken up under M&R fund during current year and last year:-
 
: N.A.
Year
Name of work  (M&R)
Expenditure
(Rs. In lacs)
Cumulative expenditure during the year